Work starts on repairs at New Brighton Pier
Christchurch City Council has embarked on a 12-month plan to repair the earthquake-damaged New Brighton Pier, with workers having started onsite as of Monday 30th January.
The repairs to New Brighton Pier will focus on damage sustained by the support columns at seabed-level, and there will be additional repairs to cosmetic earthquake damage on the deck and railings.
The Council’s General Manager City Services David Adamson explained “Fulton Hogan (builders) will be working inside caissons, which are segmented watertight tubes.
“Over the first few weeks, the caissons will be driven firmly into the sea-bed, built up around each of the damaged pier columns with a watertight seal, and then all the seawater will be pumped out.
“It’s a really interesting process that you don’t see too often in Christchurch
“I’m told it’s a bit unnerving when you’re standing under all that water, but the caissons create a safe, dry space in which to work.
“It’s also the fastest option. Some of the damage has left the Pier's support columns vulnerable to rust, and the faster we fix them, the less chance there is for them to deteriorate in the marine environment.
“This work is essential if the Pier is to have a long lifespan, so this is great news for everyone who likes to make the most of one of Christchurch’s major attractions.”
The Pier performed as expected during the earthquakes and remains safe to use and the impact on visitors to the Pier during the works will be minimised – with the exception of the occasional closure to allow contractor vehicles to come and go, the Pier will remain open to the public throughout. Popular events based around New Brighton Pier, including the Treetech Guy Fawkes Fireworks Spectacular, the Coast to Coast and the New Zealand Surf Life Saving Championships, will all go ahead as planned through 2017.
The repair project has a budget of $9.7 million, and is expected to be completed by February 2018.
The adjacent New Brighton Library is currently closed for repairs, and is set to reopen on Monday 13th February.
14th October 2016 - COMMUNITY INPUT WANTED ON BRIGHTON POOLS PLAN
28th November 2014 - BRISBANE CITY COUNCIL BEGINS REPLACEMENT OF HISTORIC SHORNCLIFFE PIER
2nd May 2014 - CHRISTCHURCH EARTHQUAKE APPEAL TRUST ANNOUNCES FINAL GRANTS
24th June 2013 - CHRISTCHURCH CITY COUNCIL PLANNING COMMITTEE RECOMMENDS NEW BRIGHTON WATERPARK STUDY
Related Articles
Published since 1997 - Australasian Leisure Management Magazine is your go-to resource for sports, recreation, and tourism. Enjoy exclusive insights, expert analysis, and the latest trends.
Mailed to you six times a year, for an annual subscription from just $99.
Get business and operations news for $12 a month - plus headlines emailed twice a week. Covering aquatics, attractions, entertainment, events, fitness, parks, recreation, sport, tourism, and venues.