Ukraine War among events reported to impact planning of Christchurch cycle ways

A report to Christchurch City Council has noted that the planning of four major cycle routes are being significantly impacted by inflation delays, unexpected ground conditions and interfaces with rail infrastructure. The report also advised that global events such as the pandemic and war in Ukraine were also having a significant impact on inflation, which has affected construction projects.

Councillors need to consider the projects’ future as the report advised of a current $25 million shortage.

The report to Councillors also said “since the projects base estimates were established, a number of other factors have driven increased costs. These include KiwiRail interfaces, project delays, contaminated material discovery and increased infrastructure renewals due to poor conditions.”

The cost of the KiwiRail component has increased throughout the life of the projects and it is very difficult to get any certainty around final expected costs.

“Delays continue to occur with KiwiRail delivery adding to project costs through resource time, costs and inflation.”

Council staff are working to find a way forward with KiwiRail to gain cost and delivery certainty and begin discussions with Rau Paenga and Waka Kotahi regarding funding and delivery.

No additional funding is needed for the upcoming financial year, so funding will be considered as part of next year’s Long Term Plan once there is more certainty about the costs.

A number of Major Cycleway projects, including the completed Rapanui-Shag Rock and the four impacted routes - South Express, Nor’West Arc, Northern Line and Heathcote Express - received funding from the Government’s ‘Shovel Ready’ programme in early 2020. This was intended to accelerate projects to reduce the economic impact of the COVID-19 pandemic.

“Shovel Ready submissions were made based on the best information to hand at the time and were often based on current budgets in the Long Term Plan without scheme and detailed designs having been completed. There was no time for risk assessments to be completed,” the report says. 

An independent quantity surveyor is reviewing remaining work on the routes to gain more confidence in the amount required to complete the projects.

Read the full Finance and Performance Committee report here

Australasian Leisure Management Magazine
Subscribe to the Magazine Today

Published since 1997 - Australasian Leisure Management Magazine is your go-to resource for sports, recreation, and tourism. Enjoy exclusive insights, expert analysis, and the latest trends.

Mailed to you six times a year, for an annual subscription from just $99.

New Issue
Australasian Leisure Management
Online Newsletter

Get business and operations news for $12 a month - plus headlines emailed twice a week. Covering aquatics, attractions, entertainment, events, fitness, parks, recreation, sport, tourism, and venues.