Timaru District Council releases concept design for Theatre Royal and museum project

Timaru District Council’s project to develop a new museum and a renewed theatre has reached another major milestone with the sign off of concept designs.

Council signed off on the concept plans at a meeting this week, enabling the project to move onto the detailed design phase.

The project, which is being part funded through the New Zealand Government’s ‘shovel-ready’ COVID-19 support fund, will break ground later this year.

In addition to floor plans, councillors were also presented with artist impressions to show the scale of the spaces.

Timaru District Council Project Manager, Nicole Timney said that although the design will evolve at the next stage, the impressions were designed to gives an indication of the scope and scale of the project.

Timney advised “the finer details of the design will evolve naturally as we move through each phase. The entire complex will cover approximately 4,430 metre², or about 17 standard tennis courts,” she said.

“The public facing theatre facilities will remain approximately the same size, but aspects such as the fly floor and the back of house facilities will be improved and changing rooms refurbished.

"The new Heritage facility will spread across three levels. The ground floor will have a reception area, a temporary exhibition space, function space, back of house facilities and an education and staff support space. The permanent exhibitions will be located on the upper floor.

Jane Rooney from Architectus said that the artist impressions indicate how Architectus plan to retain The Criterion Hotel and integrate it into the design of the complex, explaining “the heritage bluestone walls from the Criterion Hotel will be strengthened and stabilised so they can be retained.

“The original textured walls will add richness and interest appropriate to the new Heritage Facility.”

While it will be operated as one complex, there will still be two entrances to the building from Stafford Street, one through the existing façade of the Theatre Royal and one through to the foyer of the new museum to offer street level access to the whole building while accommodating the steep slope of Stafford Street.

A significant efficiency in the new complex will be the introduction of shared building services covering all areas.

Rooney added “the introduction of a central service zone between the two facilities reduces the overall size and extent of the services required.

“Not only can front of house facilities and toilets be shared but it also means there are savings on things like ductwork, pipework runs and risers.”

The report also outlined two options to provide large vehicles access to the back of the house, with Timney explaining “during consultation the limited space to safely back a vehicle up to a loading dock was identified as a major deterrent to large scale productions making use of the facility.”

The concept plan presented by Architectus seeks to overcome this limitation with a couple of options that will be decided on during the final design phase.

Timney went on to advise that “demolition works are due to start in the next two months to enable the construction of the new complex and carpark. These works are a necessary part of the development.”

The Theatre Royal and Museum Project is aiming for a completion date in 2023.

Images: Concepts for the Timaru's Theatre Royal and museum project.

Australasian Leisure Management Magazine
Subscribe to the Magazine Today

Published since 1997 - Australasian Leisure Management Magazine is your go-to resource for sports, recreation, and tourism. Enjoy exclusive insights, expert analysis, and the latest trends.

Mailed to you six times a year, for an annual subscription from just $99.

New Issue
Australasian Leisure Management
Online Newsletter

Get business and operations news for $12 a month - plus headlines emailed twice a week. Covering aquatics, attractions, entertainment, events, fitness, parks, recreation, sport, tourism, and venues.